Issuance of Occupancy and Electrical Permit

This permit is issued upon actual occupancy of constituents within the locality of Manolo Fortich, and upon request of applicants for business permit requirement.

  • Clientele: Residents, non-residents and corporations
  • Requirements:
    • Sketch of the house (contains at least two elevations, floor plan, electrical plan, vicinity/location plan)  3 copies
    • Electrical Permit Form to be accomplished in 3 copies signed by a professional Electrical Engineer and the applicant. – 3 copies
    • Application for Occupancy Permit to be accomplished in 3 copies signed by the applicant.
    • Tax Declaration or Land Title ( 3 copies)
    • Authorization or Deed or Sale if the applicant is not registered owner of the lot (3 copies)
    • Current Tax Receipt or Tax Clearance (3 copies)
    • Certification from the Barangay Chairman as to road allowance.
  • Fees: Per Assessment (NBC) – PD 1096
  • Process in availing the service:

Process to Undergo

Processing Time

Accountable Person(s)

Office Location

1. Client requests for actual site inspection of the building.

1 day

M.C. Galicia,
Roque Relosa,
Danny Lahayon

MEO

2. Client submits Certificate of Completion
(for all permanent structures)

5 days

Client

3. MEO conducts evaluation or review of the building plan and places occupancy permit number.

30 minutes/plan

M.C. Galicia,
Danny Lahayon

4. OBO approves the application

2 days/week

Engr. Ricardo Madrid

5.MEO endorses the approved plans at NSO

30 minutes

M.C. Galicia

MCR

Total Processing Time Under Normal Condition

8 days & 1 hour